THE ABS MANUFACTURING
Below is shown the ABS manufacturing story from the end first and then followed by less and less completed.
|
10.01.03


Status 30.09.02

Top view showing the support structure for the BOP/ Details of the support structure
for the BOP / wellhead wellhead being installedand housing for the ROV equipment

Side view
Status 19.08.02

|
|
The pictures show the eight compartments with bulkhead and some of the skin plates,
7.2 meters high and 16 meters in diameter.
|
Status 23.07.02

Center cone, Atlantis prototype unit Lower part of Atlantis prototype unit,
Diameter 6.5 metersOuter diameter 16 meters |
|